No | Jenis Infrastruktur | Volume | Satuan | Penerima Manfaat (Jiwa) | Total HOK | |||
---|---|---|---|---|---|---|---|---|
Total Pemanfaat | Jumlah Wanita | Jumlah Tenaga Kerja (Orang) | Jumlah HOK | Nilai HOK (Rp.) | ||||
TOTAL | 20.598 | 9.911 | 554 | 175.799 | 22.640.370.000 | |||
1 | Jalan | 12499.60 | meter | 9521 | 4645 | 281 | 101352 | 12.029.190.000 |
2 | Drainase | 8245.00 | meter | 2558 | 1264 | 53 | 14838 | 1.837.195.000 |
3 | Jembatan | 357.00 | meter | 1220 | 565 | 15 | 3030 | 363.780.000 |
4 | MCK | 45.00 | unit | 416 | 213 | 30 | 1711 | 274.430.000 |
5 | Persampahan | 128.00 | unit | 1475 | 676 | 17 | 3467 | 416.200.000 |
6 | Air Bersih | 6108.00 | meter | 417 | 203 | 5 | 2404 | 288.500.000 |
7 | Tambatan Perahu | 14.00 | unit | 1180 | 534 | 32 | 7669 | 1.123.135.000 |
8 | Sarana Ruang Terbuka Hijau | 15909.90 | m2 | 2760 | 1331 | 113 | 40800 | 6.244.420.000 |
9 | Proteksi Kebakaran | 8.00 | unit | 1051 | 480 | 8 | 528 | 63.520.000 |
TOTAL | 20.598 | 9.911 | 554 | 175.799 | 22.640.370.000 |